I have a form that automatically calculates the number of days between 2 dates, it works without problems in all months, except in September, when within the range of selected dates is September 04, it does not consider it in the calculation.
It uses as a basis for the calculation the formula that appears in the attached xls that you provided in the community forum, but it has the same problem when selecting September 04.
I would appreciate if you could help me to solve this problem.
I made several tests, but when I included September 04 in the date range, the problem reappears… with other date ranges the function works without problems.